Project : Basal Treatment of Engineered Landfill Cell using Lime Stabilisation at Pulau Burung Sanitary Landfill, Penang

Project Brief:

  1. Lime stabilization for construction of stabilized subgrade of 300-350mm thick at the base and side slopes of the engineered landfill cell (first cell)
  2. Subgrade materials are of marine clay nature which is soft, soggy, and with low permeability
  3. Completed the first cell in June 2019